Monday, April 6, 2015

DPWH XI implements P14-B projects on 2015



DAVAO DEL NORTE, April 6, 2015 – The Department of Public Works and Highways (DPWH) will implement around P 14-billion projects in the different parts of Region XI this year 2015.

DPWH XI Regional Director Ramon Alquiza revealed during their regular monthly press conference on Friday (April 3) held at the Davao del Norte District Engineer’s Office that the region has identified 723 projects for completion this year.

“Our priority this year is in line with the priority of DPWH Secretary Rogelio Singson that is to pave all national roads,” RD Alquiza said.

Alquiza said that the region has a total of 1,668 kilometers of national road, which is composed of 844 kms. of primary roads and 824 secondary roads.

He said that among the primary roads were 329 kms. north-south backbones and 133 kms. of east-west laterals.

He said that for the period of January to March, only 2.95% of the projects have been accomplished.

He disclosed that out of the 723 projects, one project was completed, 183 already started and 539 had not yet started.

“We only have a minimal accomplishment for now since this year, we have plenty of projects and most of the projects have been bid out from January to March,” he said.

He disclosed that unlike on 2014 with 358 projects costing around P 8-billion, most of the projects were bid on December of 2013.

“I must admit that we are quite late in starting the projects this year. Because of the number of projects, we were having a hard time catching up with the program of works, estimates and preliminary surveys,” he said.

Alquiza said that he augmented two more survey teams in the regional office to fast track the materialization of the projects. (PIA11, Michael Uy)