Plant Manager Belinda May F. Rom guaranteed good performance of her full pledged team.

Logically, the processing plant needs 49 workers: this includes 10 fulltime decorticator, 15 dryers, 10 husk haulers, 10 common laborers, and 4 baling press operators.

The total plant cost covers the completion of decorticating machine, husk conveyor, fiber cleaner, baling press machine, delivery truck, construction of decorticating building, baling press building, retting pool, power supply, welding machines and tools.

Rom is very confident that her team, with the supervision of DOCHSEi’s Board of Trustee will do its best to stabilize the needed resources for the plant operations and success. They are very hopeful that sooner, the plant could expand and generate more workers for the development also of the province & incorpration. (By Analyn S. Padullon and Van Jorain O. Rufin)