Wednesday, March 7, 2012

Switching power interruptions set on March 11


Davao Light and Power Company will conduct switching power interruptions on March 11, Sunday, affecting the customers in portions of Downtown, Matina and Ecoland areas.

Corporate Communications Officer Ross Luga said that the service interruptions are necessary to conduct a corrective maintenance servicing to its Ecoland Substation.

The first set of power interruptions will take place from 2:00 AM to 2:45 AM for the transferring of loads to Ponciano substation and from 11:00 AM to 11:45 AM for the normalization.

Affected by these service interruptions are the power consumers in the entire Maa, those from Las Terrazas in diversion road up to Langub and Magtuod and those from corner diversion road going to Energy FM in Shrine Hills.

Juna Subdivision, Ecoland Phases 2 and 4, Ecoland Terminal, SIR Matina and Sandawa will also be experiencing the said outages.

On the other hand, the second set of switching power outages will be from 2:30 AM to 2:45 AM and from 11:30 AM to 11:45 AM that will affect the customers situated along Quirino Ave. from corner Mabini St. up to Bankerohan bridge, in portion of Fr. Selga St. and from Quirino Ave. to corner Anda Magallanes.
Also affected are Gen. Luna and Duterte Sts., part of San Pedro St. from Kusina Dabaw to corner Ilustre St. and Legaspi St., from Davao City Central Convenience Store to corner Legaspi and Magallanes St.

Davao Light apologizes for the inconvenience of these service interruptions but it will exert all efforts to restore electric service as scheduled or earlier. However, there may be instances where restoration may extend beyond the schedule due to unavoidable circumstances.

To receive scheduled power interruption announcements through e-mail, please send your Davao Light Account Number todavaolight@aboitiz.com. (DLPC PR)