Davao Coal-fired power plant eyes operations by early next year



DAVAO CITY- The 300-megawatt coal-fired power plant in Davao City is eyed to start its commissioning and operations by the first half of 2015 this was revealed by Aboitiz Power corporate communications manager Willy Rodolfo.

"It's about 90% complete and we're right on schedule." Rodolfo said during Monday's (Nov. 10)  Kapehan sa SM.

He added that within a few months they would be able to testing the plant. "testing means practically running the plant but not on a continuous basis." Rodolfo added.

The plant if it would start operating would boost power supply to the major cities of Mindanao except Zamboanga. The plant will supply the power needs of 22 power cooperatives across Mindanao.

Franchise areas under Davao Light and Power Company (DLPC) will benefit from the operations of the coal plant as it has contracted 100 megawatts from its load.


Rodolfo also added that the they are on track in meeting the requirements of the Davao City Sangguniang Panglungsod (City Council).

Among these is the utilization of surface water to cool the plants instead of extracting underground sources and also the implementation of the carbon sink for the plant. The company is currently implementing its 500 hectares carbon sink in Marilog. where farmers/partners are already trained in the agro-forestry program and are now capable of re-echoing it to the community. (PIA/RG Alama)